Visited on May 19 to see the new setup.
Based on the live data, the timeline seems to have been as follows:
In the evening of 2024-12-15, the site was brought offline. At the end of the day on 2024-12-16, the second charger was put into service. In the morning of 2024-12-18, the existing EVTEC was finished swapping with an Alpitronic and put into service.
The new charger uses the existing concrete foundation that was there from the start.
This upgrade must have coincided with a grid upgrade, because otherwise they could already have put a 300kW charger the last time they swapped the EVTEC with another EVTEC.
There is still the same ban sign, and still no clear lines, so there's a risk there might not be enough space for 4 cars if anyone parks badly. There's no mention 4 spaces should be left available, restaurant customers might have no idea how much space they are supposed to leave.