Visited on July 12 and charged with Electra RFID, no issue.
On my last visit I missed the fact the CCS cables had been replaced and the chargers re-branded as 300kW, so I tried the new longer cable on charger 2.
Contactless didn't seem to work on units 2 and 1. But it was working on unit 3.
Unit 1 in the middle is still advertising 161kW on the screen. Now Unit 2 also shows the same mysterious 161kW. This seems to suggest there are at least 3 power modules / 225kW. But because of that information I'm skeptical 300kW is possible at all, be it for lack of power modules, or grid limit. Likewise while I assume all power modules are in the HYC_400 I would be surprised if 400kW can actually be reliably achieved.
AC on unit 2 is still there but was showing out of service. According to the live data, it's only out of service from time to time, and that included that Sunday afternoon. But nobody has charged on AC since unit 2 was brought back in service on or around 2026-05-20, so I think it might be broken even when the live data shows it available. If it's ever available when I visit I'll try to charge on it.
At this time, the metadata for the connectors doesn't seem to have been updated in the systems. MOVE and Swisscharge still show the CCS at 150kW, and 2B still as a CHAdeMO.